Project Name: Dscovery at Marigot Bay, Marigot Bay, St. Lucia, West Indies.
Client: Doubloon International Ltd.
Delivery Methodology: JCT
Standard Form of Building Contract with Contractor's design 1998
Edition incorporating Amendments 1,2,3 and 4 abd the sectional
completion suppliment.
Building Type: Mixed - use scheme including, central facilities building, condominium units, resort amenities and landscaping.
Project Overview: Luxury
condominium project comprising 19 number building units, plus a large
central facilities building, (refurbishment and extension to existing
heavy masonary building) pool complex, porte cochere, extensive
landscaping, retaining walls and site services.
Challenges:
Construction logistics, major earthworks cut and fill operationbs on
steep slopes and piling works on marsh land at the toe of the slope
adjacent to the associated marina development.
Contract Value: US $19.2m
Construction schedule: Contract duration 21 months. Works currntly ongoing and to programme.
Estimate Methodology: Competitive
1st stage bid on 80% drawings leading to selection for 2nd stagew open
book negotiation and finalization of design and novated design team.
Package Strategy: Johnston as the main cotractor is using its preffered supply chain partners as appropriate, with emphasis on local suppliers.
|