Project Name: Leeward Marina, Resort and Spa, Turks and Caicos.
Client:
Leeward Resort Limited.
Delivery Methodology:
Negotiated Lump Sum Contract.
Building Type:
Residential and Commercial.
Project Overview:
The
Leeward Marina Project comprises an Upscale Resort with
condominiums, boat storage, restaurants, commercial space and a 110
slip Eco - Marina together with the construction of 41 canal side
homes.
Challenges:
The
excavation of the marina
basin and adjoining canal s will require the excavation of 130,000
cubic yards of material under water, the dredging of a marina approach
from the sea following strict guidelines laid down by the Turks and
caiocos Islands Department of Environmental and Coastal Resources.
Additionally the project involves the installation of 4500 linear of
dock wall and capping beams.
Contract Value:
US $100m
Construction Schedule:
The mobilization date for the project is the 1 July 2005 and the contract duration is 36 months.
Estimate Methodology:
Negotiated lump sum.
Package Strategy:
|